Civil & Structural Design & Engineering

Site grading, steel structures, foundations, buildings and site works for substations, pooling stations, BESS sites and HVDC station yards, designed from the approved layout, equipment loads and geotechnical data.

Generic switchyard gantry elevation with flexible bus and foundation reactions
Generic illustration of a gantry bay elevation.

Section 01

Design basis and information inputs

Civil and structural design depends on information that arrives from several directions, so the first step is to list what is needed and who supplies it. We work from the approved general arrangement or layout; the wind and seismic zone and the loads the client specifies; the geotechnical report with bearing capacities and founding levels; architectural and building requirements; equipment terminal loads and dimensions; anchorage and foundation reaction schedules from vendors; the structural codes the client and national practice require; and drainage and grading constraints for the site.

Inputs that are missing or still preliminary are recorded in an interface and input register with the date each is needed. Design is not advanced on unconfirmed data without the assumption being written down and agreed.

InputTypically from
Approved layout and GAElectrical design
Wind and seismic criteriaClient specification
Bearing capacity, founding levelsGeotechnical report
Equipment loads and dimensionsVendor drawings, GTP
Building requirementsClient, architect, services
Survey levels, plot plan, drainage constraintsSite survey, client

Section 02

Switchyard structures

Switchyard structures carry conductors, equipment and lightning protection: steel gantries, towers and line termination structures, equipment support structures, bus support and portal structures, lightning masts and shield-wire supports. Loads come from the electrical design (conductor tensions, equipment weights and terminal loads, wind and, where relevant, short-circuit forces) and are combined into load cases under the project code: dead and imposed loads, wind, seismic, conductor tension, short-circuit forces, and erection and maintenance loads.

We size members and connections, design bolting and base plates, check load combinations, and prepare analysis models for review. Where fabrication and erection drawings are assigned, we produce them from the same model so the drawings match the calculation.

Structures

  • Steel gantries, towers and line termination structures
  • Equipment support structures
  • Bus support and portal structures
  • Lightning masts and shield-wire supports

Design work

  • Member sections and connections
  • Bolting and base plates
  • Load combinations
  • Analysis models
  • Fabrication and erection drawings, if assigned

Section 03

Foundations and RCC

Illustrative transformer foundation with oil pit, gravel layer and drain to a sump
Equipment foundation and oil containment section. Generic illustration.

Foundations include those for transformers and reactors; isolators, circuit breakers, current and voltage transformers and arresters; equipment support pedestals; gantry and tower footings; control building foundations; and cable trench or cable bridge foundations.

Footings and pedestals are designed for bearing, uplift, overturning and sliding against the allowable soil pressures in the geotechnical report, with settlement considered where the inputs allow. Anchor bolts and embedments are designed with the foundations. Reinforcement details, schedules and bar bending schedules are prepared when they are in scope. Foundation bolt positions and oil pit dimensions follow the approved vendor drawing, which is why vendor data are verified before foundation drawings are issued.

Section 04

MCR, control room and GIS buildings

For the main control room (MCR), relay or GIS building, we prepare the general arrangement, architectural layout as required, and the structural design of the frame: foundations, floors, columns and beams, slabs and roofing. Equipment rooms, cable entries, trench penetrations and openings are coordinated with panel and cable layouts, and the building layout follows the approved architectural and services information.

Building utilities such as HVAC, fire protection, plumbing and building electrical services are designed by their specialists. We take their requirements as inputs and coordinate the openings, loads, supports and architectural interfaces they need.

  • General arrangement and room layout
  • Roof, beam, slab, column and footing design
  • Equipment room and cable entry interfaces
  • Trench penetrations and openings
  • GIS building slab, crane and embedded item interface

Section 05

Civil infrastructure and site works

Site works tie the yard together: grading and earthwork, drainage and rainwater networks, cable trenches and duct banks, roads and paving, transformer oil containment, bund and sump arrangements as specified, retaining works where levels require them, fencing and boundary walls, yard facilities, and the equipment access that lets the station be operated and maintained.

These drawings are checked against the electrical layout, so that a trench does not cross a foundation and a road does not leave a transformer without access for delivery or maintenance.

  • Site grading, plot plan and earthwork
  • Drainage, rainwater and stormwater network
  • Cable trenches, duct banks and crossings
  • Roads and paving
  • Oil containment, bund and sump, as specified
  • Retaining works, where levels require them
  • Fencing, boundary wall and yard facilities
  • Equipment access and operability interfaces

Section 06

Civil works by infrastructure type

InfrastructureCivil and structural focus
AIS/GIS substationsGantries, equipment supports, transformer and reactor foundations, control and GIS buildings, trenches, roads, drainage
Pooling substationsPooling transformer foundations and oil containment, MCR building, collector cable trenches, grading
Solar and wind plantsInverter and transformer skid foundations, cable trenches, roads and drainage, as contracted
Battery energy storageContainer and PCS foundations and plinths, cable trenches, drainage, access for maintenance and emergency
HVDC stationsConverter transformer foundations, firewalls, oil containment, yard structures and buildings, as contracted

Section 07

Output categories

Five groups of outputs. A package may include some or all, depending on the scope agreed.

A

Structural design calculations

Load cases, analysis and member checks for each structure type.

B

Foundation calculations

Bearing, uplift, overturning and sliding checks against the soil data.

C

GA, layout and infrastructure drawings

Structure GA, foundation layout, trenches, roads, drainage and site plans.

D

Detail and reinforcement drawings

Reinforcement details, bar bending schedules and member schedules.

E

BOQ, MDL and coordinated issue set

Material estimates, the civil MDL and, where approved, a coordinated set issued for construction.

Open the civil and structural deliverables library

Section 08

Design interface examples

When this changesThis is affected
General arrangement or equipment positionFoundation centre-lines, levels, trench routes
Conductor tension, wind or short-circuit loadsGantry member sizes and footings
Transformer or equipment vendor drawingFoundation bolts, plinth, oil pit dimensions
Geotechnical report or founding levelFoundation type, depth and reinforcement
Cable routingTrench layout and control room penetrations

Interfaces are tracked in a register so that a change in one document is traced through the drawings that depend on it.

Submit your SLD, GA, geotechnical data and civil MDL

Send the approved layout, the geotechnical report, the equipment drawings and the civil deliverable list. We will confirm the inputs we still need and a sensible submission sequence.